PennDOT says seal coating work on Renovo Road to begin Monday, June 26

LOCK HAVEN, PA – PennDOT has posted signage adjacent to Hanna Park in Lock Haven alerting motorists that seal coat work on the Renovo Road will begin on Monday, June 26. That posting follows word that initial project work is to begin on Tuesday of this week starting on the Kettle Creek Road.

The schedule as announced earlier:

• The first two days, June 20-21, work will take place along State Route 4001 (Kettle Creek Road) from the intersection of Route 144 in Cross Fork to Whiskey Springs.
• Seal coating will then move to Route 144 South, starting just outside South Renovo Borough to the Centre County line and back, a several-day project.
• Work then moves from South Renovo into Renovo along Route 120, initially coming south down to just past Hyner, then continuing down to Hanna Park/Sugar Run Road in Lock Haven.
• As seal coating work heads north along Route 120, crews are also slated to seal coat State Route 1014 (Hyner Mountain Road), then come back and complete seal coating along Route 120 to the bridge heading into Renovo.
• A final section of seal coating will be done along State Route 1002, Island Road, starting under the Constitution Bridge and down to the second Island Bridge and back.

Back to top button