Work on state highway projects update
WESTPORT, PA – PennDOT has released its weekly update on multiple highway projects across Clinton County. One of them, on Route 120 near Westport, is nearing completion.
HRI, Inc. is the contractor on that work. PennDOT says the contractor will begin paving operations and removing the long-term traffic control. HRI will then complete the project drainage and roadway work. Temporary daylight traffic control, using flaggers, will remain in place until roadway reconstruction is completed. Signal lights are also in use in the work zone.
Estimated project completion is late August to early September.
The status of other projects, per PennDOT:
State Route: 150 (Flemington Bridge) – HRI, INC. – Contractor will be working on structural steel repairs. Olympus will be painting the bridge. Traffic control: The bridge is closed. Please follow the detour. No pedestrian crossing. All work is weather dependent. (PennDOT recently announced the heavily used bridge will not be ready to one-lane traffic for the start of the new school year later in August).
The following work is scheduled to be completed by contractor, weather permitting: State Route: 1001 (Farrandsville Road) – Clearwater Construction, Inc – Piles are finished. Contractor will be drilling and installing tie-back anchors and installing precast wall panels. Traffic control: Motorists will encounter daily lane closures regulated by flaggers. NO PEDESTRIAN TRAFFIC THROUGH THE WORK ZONE WILL BE PERMITTED.
State Route: 120/220 (Paul Mack Blvd) – Bruce and Merrilees Electric Company – Contractor will be working on the traffic signal turn on Tuesday, and sign lighting and cameras on SR220. Traffic control: Motorists will encounter daily shoulder closures at the SR220 north bound and south bound off ramps at the Lock Haven exit.
State Route: 150 (Chatham Run Bridge) – HRI, INC. – Contractor will be working on concrete repairs. Traffic control: Flagging operations will be used as required to perform work. All work is weather dependent.
State Route: 1002 / 64 (Great Island Road / Lamar Bridge spanning Fishing Creek) – RAM Construction Services of Michigan, INC. – Contractor will perform epoxy-based surface treatments on bridge decks, from 8/20/23 through 8/23/23 on Island Road and 8/18 through 8/19, in Lamar, spanning Fishing Creek. Traffic Control: Work will be done under daily daylight single lane closures. Motorists are advised to watch for slow moving and stopped vehicles through the entire work zone. Use caution when traveling through the work zone and obey the posted speed limit. All work is weather dependent.
State Route: I-80 East and West in the Loganton / Carroll locations – Glenn O. Hawbaker – Contractor will be working on bridge deck and approach slab repairs by doing concrete replacement. Traffic Control: Traffic is restricted to one lane. Watch for construction vehicles entering and exiting the project. All work is weather dependent.